Sout Burlington, Georgia Design Build

The Project consists of replacement of six Culverts at three locations on I-89 in the towns of South Burlington and Georgia VT.  The Georgia culvert replacement will be done by the Sequential Excavation Method (tunneling).

The Project is a Design-Build whereas the Contractor and the Design team combine to one entity.   The purpose is to deliver to the Vermont Agency of Transportation (VTrans) a quality project with a long life span. 

The existing culverts are Corrugated Metal Pipe (CMP) in poor to serious condition, with failure inevitable in the near future.   The Design-Build team plan to replace these culverts with Precast Concrete Structures of varying configurations.    